Boris’s cycle hire scheme to lose £35m over next three years

March 26, 2013 - Martin Hoscik@MayorWatch

cycle_hire_logo_closeLondon’s cycle hire scheme is expected to lose almost £35m over the next three years.

Figures provided by Mayor Boris Johnson to London Assembly Member Darren Johnson show the scheme, which was originally promised to be self-funding, will lose £11.6 million in 2013/14.

Further losses of £10.7 million are projected in 2014/15, with loses in 2015/16 expected to total £12.6 million.

City Hall has calculated the losses as the difference between the membership and usage fee receipts and the operational costs per year.

The scheme is proving to be a financial black hole for Transport for London, with construction and runnings costs projected to total more than £225m by 2015/16.

Last year TfL was forced to reveal that less than £14m of the £50m sponsorship money promised by Barclays bank has been received.

In order to plug the gap in the scheme’s finances TfL and the Mayor have announced a doubling of usage fees, a move the Mayor previously revealed would raise an additional £6m per year.

Local councils have also been told that expansion of the scheme into their boroughs is “conditional” on them providing £2m each, despite being asked by Central Government to reduce expenditure.

So far more than £6m has been raised from the boroughs, many of which have sought to pass on the costs to developers via Section 106 agreements, thereby increasing the cost of developing in the capital.

Details of the projects loses were revealed in answer to a written question to Green party AM Darren Johnson.

In his answer the Mayor said: “The recent tariff increase and the expansion to West and South West London later in 2013 are likely to have a significant impact on both income and costs for Cycle Hire, and it is too early to have a full understanding of what these will be.”

TfL has already admitted it has no idea when the scheme will break even.

Commenting on the Mayor’s answer, Assembly Member Johnson said: “These figures are not at all surprising. The cycle hire scheme was unlikely ever to be self-financing – public transport rarely is. But the Mayor should have thought this through before making such rash promises about cycle hire not requiring public funding.”

  • Click to share on Twitter (Opens in new window)
  • Click to share on Facebook (Opens in new window)
  • Click to share on Tumblr (Opens in new window)
  • Click to share on Pinterest (Opens in new window)
  • Click to share on LinkedIn (Opens in new window)
  • Click to share on Reddit (Opens in new window)
  • Click to print (Opens in new window)
  • Click to email this to a friend (Opens in new window)

Tagged With: Cycle Hire

RECENT UPDATES

TfL proposes bus and tube cuts and annual fares increases to achieve long-term financial sustainability

London’s entire bus fleet now meets ULEZ emissions standards

New road layout comes into effect at Old Street roundabout

TfL funding enables creation of 2,000 new cycle parking spaces




Popular

1,700 extra Santander Cycles are coming to London’s streets

TfL confirms changes to Older Person’s Freedom Pass and 60+ Oyster card hours

TfL fares to rise in return for £1.6bn Government rescue package

Election for Mayor of London and London Assembly postponed until 2021

FEATURED

City Hall to move to Docklands as Mayor seeks to raise £55m for frontline services

‘Concern’ over TfL’s ability to deliver major projects in wake of Crossrail cost overruns

City Hall halts London Overground ticket office closures but many will still see opening hours reduced

Transport for London confirms bus cuts will go ahead despite passenger opposition

GOT A STORY?

As the original London news and scrutiny site we've been casting an eye over the capital's public services and politicians since 1999.

 

Many of our top stories started with a tip-off from a reader - if you've got something you'd like us to cover get in touch and we'll do the rest.

Stay In Touch

  • E-mail
  • RSS
  • Twitter

Copyright © 2021 MayorWatch Publications Limited · MayorWatch is Registered Trademark · All Rights Reserved · Contact Us · Terms of Use · Privacy Policy

MayorWatch Publications Limited · 20-22 Wenlock Road · London N1 7GU · Company Number 6291816

loading Cancel
Post was not sent - check your email addresses!
Email check failed, please try again
Sorry, your blog cannot share posts by email.